| Construction
Linked Plan |
| At the time of booking/Allotment |
15% of BSP |
| On start of Excavation |
10% of BSP |
| On Casting of Foundation / Raft |
10% of BSP + 50% PLC (if any) |
| On casting of stilt / Basement Roof |
10% of BSP + 50% additional Charges |
| On Casting of ground Floor roof |
10% of BSP |
| On Casting of first Floor roof |
05% of BSP |
| On Casting of second Floor roof |
05% of BSP |
| On Casting of third Floor roof |
05% of BSP |
| On Casting of Fifth Floor roof |
05% of BSP |
| On Casting of seventh Floor roof |
05% of BSP |
| On Casting of nineth Floor roof |
05% of BSP |
| On Completion of Internal Plaster |
05% of BSP |
| On Completion of Flooring |
05% of BSP + 50% PLC( if any) |
| On offer of possession |
05% of BSP+50% additional Charges+other Charges(if any) |