| Triveni Galaxy(Standard) Price |
| Size |
Area (Approx) |
PRICE (PER SQFT) |
Booking Amount |
| 2 BR |
1170 Sq. ft. |
1900 |
35% |
| 3 BR + 2T |
1495 Sq. ft. |
1900 |
35% |
| 3 BR + 3T |
1705 Sq. ft. |
1900 |
35% |
| 3 BR + 3T + S |
2090 sq. ft |
1900 |
35% |
| 4 BR + S |
2250 Sq. ft. |
1900 |
35% |
Specification:-
*Deluxe =Rs. 150 extra
*Luxury =Rs. 350 extra |
| Triveni Galaxy sec-78 |
| |
March status |
April Status |
| Tower |
Work in progress |
Work in Progress |
| T-1 |
Foundation |
2nd Floor Slab |
| T-2 |
Ground Floor Slab |
1st Floor Slab |
| T-12 |
2nd Floor Slab |
5th Floor Slab |
| T-13 |
Basement Slab |
2nd Floor Slab |
| T-14 |
1st Floor Slab |
5th Floor Slab |
| T-15 |
Basement Slab |
1st Floor Slab |
| T-16 |
3rd Floor Slab |
7th Floor Slab |
| T-17 |
1st Floor Slab |
6th Floor Slab |
| T-19 |
Foundation |
1st Floor Slab |
| Down Payment Plan* with 7.00% Rebate..................."A" |
| At the time of Registration |
35% of BSP |
| With in 45 Days of launch |
63% of BSP + 100% PLC(if any), !00% EDC & 100% IDC + 100% EEC + 100%FFC + 100% of all Additional Charges |
| On of offer of possession |
2% of BSP + Stamp Duty and other Charges as applicable |
| Construction Linked Installment Payment Plan*..............................."B" |
| At the time of Registration |
35% of BSP + 50% of PLC(if any) + 50% EDC + 50% IDC |
|
Recent Comments
|
Latest Construction Status
|