| CONSTRUCTION LINKED PAYMENT PLAN |
| Booking Amount |
6 lacs / 7 lacs / 9 lacs |
| Within 75 days of Booking |
Complete 20% of BSP
|
| Within 150 days of Booking |
10% of BSP + 50 % of DC |
| At the Start of Construction |
10% of BSP + 50 % of DC |
| On casting of Ground Floor Roof Slab |
10% of BSP + 50 % of PLC |
| On casting of First Floor Roof Slab |
10% of BSP + 50 % of PLC |
| On casting of Second Floor Roof Slab |
7.5% of BSP + Club Membership |
| On Completion of brick work |
7.5% of BSP |
| On Completion of Internal Flooring |
7.5% of BSP |
| On Completion of External Plastering |
7.5% of BSP |
| On offer of Possession |
10% of BSP + IFMS + PBIC + Stamp Duty+ Registration Charges &
Administrative Charges |
| DOWN PAYMENT PLAN (With 10% rebate) |
| Booking Amount |
6 lacs / 7 lacs / 9 lacs |
| Within 75 days of Booking |
Complete 90 % of BSP + 100% of Additional Charges# |
| On offer of Possession |
10 % of BSP + IFMS + PBIC + Stamp Duty+ Registration Charges &
Administrative Charges |
| # Additional Charges include PLC, Club Membership & DC. |
| |
|